Microsoft Visual Studio Scrum 1.0

Microsoft Free

A new Team Foundation Server process template for Scrum teams. Product Backlog Items, Sprints, Velocity, Sprint Burndown...

Microsoft
(47) Review
Visual Studio
2010
Download (139,499)
11/4/2010
1.0
E-mail Twitter del.icio.us Digg Facebook
Add to favorites
Description
Reviews (47)
Q and A (121)
Sign in to write a review
Sort by:

by Shreeharsh Ambli | April 17 2014

this is the only reason i first got on to Scrum templates - gd work!

by David Musselman | October 02 2013

Is there a version of this for Scrum 2.2?

by D. Chatterjee | May 20 2013

Seems good, does this supports all charts?

by Sergio Parra | April 27 2013

Really a very good template!

by M.Radwan-MVP | August 23 2012

by FizzCyp | July 19 2012

by Laurent Jordi Innovacall | June 30 2012

Hello,
I know this process template is well done and necessary for my team BUT !
It doesn't work on a french TFS Server with it's french portal.
I tryed 1000 things I still have the TF249033 error

le modèle de site n'est pas disponible pour l'identificateur de paramètres régionaux (LCID). Le nom du modèle de site est : TFS2010 Agile Dashboard. Le LCID est : 1033. (type TeamFoundationServerException)

The process template is not available for this LCID... bla bla bla ... LCID is 1033

I absolutely need this process template and the sharepoint and reporting services.

Please, publish a procedure to install this project template on a French TFS Server.

Best regards,

Laurent

by usjunior | June 22 2012

by Mr. Wharty | June 08 2012

Thanks for posting

by DRiley5998 | June 01 2012

Will not install,

Event Description: TF30162: Task "WITs" from Group "WorkItemTracking" failed
Exception Type: Microsoft.TeamFoundation.Client.PcwException
Exception Message: Object reference not set to an instance of an object

by ezien | May 08 2012

by Dragan Radovac | May 06 2012

by Mattias Sköld | May 05 2012

A good template for running scrum projects, the burndown detects current sprint and makes it much easier to change sprint.
One thing that could be improved is support for multiple teams.

by Sofwarer | April 30 2012

iyi bir eklenti olmuş

by Ahmed Naji | April 02 2012

This is great template,our productivity increased now
Thank you Microsoft

by Code Chief | February 05 2012

Use this template as standard for all projects. SCRUM is great!

by TerrenceCheng | January 14 2012

Great job!.
But i have a question. today is the end of a scrum project. I want an amount of all initial task time. so that i can get if my team member's work good or bad. and so that i can make a report to my boss: how much works we finished.

now, in this project, the "remaining work" field is changed from "10" to "3", at last, when the state changed to "Done", the remaining work field's value is no longer exist.

how could i get the initial "remain work" value ?

thanks in advance.

by dsnook2 | November 10 2011

by Daniel Cheida | November 06 2011

Favorite

by Bob Cornelissen | September 04 2011

Thanks for adding this

1 - 20 of 47 Items   
Sign in to start a discussion


  • Display PBI changes in Releaes Burndown
    1 Posts | Last post July 08, 2011
    • How do I show newly added PBIs in Release Burndown chart? For example: When I started Sprint 4 I have  PBIs with an effort of 80. If I complete 10 effort points in Sprint 4 and add another 8 effort points, Release Burndown will show that I have 78 effort points remaining in the beginning of Sprint 5. This is ok but how do I show that I have completed 10 points and added 8 new ones. Is there a way to show that using this template?
  • Release Burndown is empty
    3 Posts | Last post July 08, 2011
    • My Release Burndown chart does not show any bars even though the x-axis shows all the sprints that I have defined. The product backlog includes PBIs with the status of New, Approved, Committed and some Done. I am currently on the first Sprint and the Sprint Burndown seems to be working fine. I was expecting that the Release Burndown will show the total effort remaining before I started Sprint 1. Subsequently, after the end of Sprint 1, I expect that the bar showing remaining effort for Sprint 2 will show up in the Release Burndown chart. So far, I haven't seen any bars at all. Is there something that I am missing?
    • Do you have dates associated with your Sprint WITs?
    • I created the product backlog list after the start date of Sprint 1. I figured that is why there is no bar in Release Burndown for Sprint 1. Starting Sprint 2 it showed up fine.
  • Cannot track work done on a task level
    9 Posts | Last post June 24, 2011
    • Hi Aaron,
      
      I write an open source tool for TFS called Scrum Sprint Monitor and I was looking into your process template in order to give early support for it. One thing I noticed is that the template for Tasks does not track the work that has been done on that particular task (Microsoft.VSTS.Scheduling.CompletedWork), only the remaining work. Is that something you are considering adding to the template?
      
      Thanks,
      Pedro
    • We have considered it, but have purposely left it off (for now).  Most Scrum teams I talk to are concnerned only with remaining work.  Completed work is "interesting"... but remaining work is what drives a Scrum team through a sprint.  Our goal with the template was to nail the basics that apply to all teams.  I'd love feedback on this however.  Are others interested in completed work?
    • IMHO, Completed Work is noise in Scrum. I am even glad to see that Estimated Work is not used in the template. What we have seen is that Developers would have a tendency to simply subtract Remaining Work from Estimated Work (i.e. MSF Agile) and apply that to Completed Work just for sake of filling the field. You get no real benefit of tracking just a false sense of where you are. Reality is that you can be at 99% completed for 50% of the time it really takes to complete a Task.
    • Hi Aaron,
      
      I understand your point lefting CompletedWork field off, but when I try to view the Sprint Tasks inside MS Project I get the following error message related to this field:
      
      
      ---------------------------
      Microsoft Office Project
      ---------------------------
      TF82024: The following fields could not be mapped because the fields could not be found on the server: Microsoft.VSTS.Scheduling.CompletedWork;Microsoft.VSTS.Scheduling.OriginalEstimate
      ---------------------------
      OK   
      ---------------------------
      
      What can I do?
    • @Juliano, have you considered copying the definitions of these fields from the Task work item in the MSF Agile 5.0 process template? That will allow you to open the query in MS Project and see the Tasks. You can also decide whether or not you need to display these in the UI through the Work Item editor. You can use the Process Template Editor that is part of the TFS 2010 Power Tools, if you did not already know about it, to make these definition changes visually.
      
      @Aaron, perhaps there's an improvement to the Task work item in the TFS Scrum process template where these fields are included but not displayed in the UI in order to support MS Project without errors. The problem is similar to what Donovan described earlier regarding the builds. Maybe there's a case here for compatibility.
    • Good suggestion Leo.  
    • Aaron, I brought up Microsoft.VSTS.Scheduling.CompletedWork by mistake. What I meant to ask is about an original estimate. It is very important for my tool to have an idea of what the original estimate was for a given task (and I believe it is beneficial for anyone who is looking at a task to know that as well).
    • I have noticed a tendency of some developers to have just "1 day remaining" on a task every day for weeks. We were using a tool previously that allowed you to enter the effort spent today, and it would add that to the completed work field. That is useful in determining how (a) the project manager's initial estimate (b) the programmer's detail estimate and (c) the actual amount of time spent compare. This allows project manager and programmer to see weaknesses in estimating and work to improve. How can I do that with the TFS Scrum template?
    • the tendency to leave "1 day remaining" is a missunderstanding of how remaining work is identified perhaps.  looking back, if there was really one day remaing it would be completed.  so developers are often unwilling to update the days remaining by ADDING days such that it would now say 2 days or 3 days remaining. rather than leaving it 1 day and trying to invisibly catch up. right after SCRUM the first day that this is not zeroed out..SCRUM MASTER and developer should discuss what the actual remaining is and update accordingly.
  • Release Burndown showing remaining effort for all Iterations
    4 Posts | Last post June 10, 2011
    • My release burndown chart is showing the cumulative effort for all iterations including those outside the current release.  Only Release 1 iterations are shown in the Sprint drop down if I go to the Report site, but it seems to have little affect.  What would cause this?
    • I'm also having some issues with the Release Burndown showing more points remaining than I have in my Product Backlog. Any news on an update? Am I misreading this report?
    • Same problem here...
    • I just got into the same problem...
      
      Seems like a known issue:
      http://connect.microsoft.com/VisualStudio/feedback/details/642836/vs-scrum-release-burndown-does-not-filter-by-release
  • Sprint Burndown missing all todo tasks
    4 Posts | Last post June 09, 2011
    • Our current Sprint (first running with this template) show a Sprint burndown with only "In Progress" tasks, none of the todo items are shown, even if the report states it should...
      
      What can we do to get the full report? Are we missing something in the setup or are there other issues we should look at to solve the issue?
    • 2re
      There should be no extra steps needed. Here is a few things that you can check:
      
      * Make sure that the Todo items has the correct sprint in iteration path. Two sprints in different releases can have the same name which can make it hard to spot the error.
      * Make sure that you do not have overlapping sprints by running the sprint query and verifying the dates
      * Make sure that the cube is up-to-date by confirming the "Data Updated" timestamp in the button of the burndown is reasonable present.
      
      I hope that you resolves the issue.
      
      / Tore Østergaard
    • Unfortunately that did not help. I've also tried to create a task on a user story/product backlog item that contained in progress tasks. These are show in the report but the new task did not show up either.
    • I am having the same issue.  Did you find any resolution?
  • Any target release date and/or feature (backlog) list for next version?
    1 Posts | Last post May 23, 2011
    • I would welcome one or the other.  We've enjoyed using this template but would really would like to know when and/or what the next version is?
  • Actual Hours, Estimated Hours, Remaining Hours
    3 Posts | Last post May 18, 2011
    • Is there any guidance on how to customize the template to include sprint and task actual hours, estimated hours, and remaining hours.
    • I need to add similar fields as well and wondered if anyone has sucessfully archieved this?
    • If you need those fields you may want to use the MSF for Agile template.  Scrum has no concept of actual or estimated hours, only remaining hours.
  • Users removed from TFS 2010 at night and cannot subsequently add the users via Team Explorer Error: TF50235
    1 Posts | Last post May 10, 2011
    • I raised this over in the 'Team Foundation Server -General ' forum on MSDN.
      However, since I am using the Microsoft Visual Studio Scrum 1.0 template, the Microsoft representative that replied suggest I also raise it here....
      
      http://social.msdn.microsoft.com/Forums/en-US/tfsgeneral/thread/ddc5f1cd-d211-43b0-92d1-c099056c28a7
      
      Essentially some TFS users are loosing access to TFS project each night and when I try re-add the the next morning using Team Explorer I get the following error
      
                     TF50235: The group Contributors already has a member [UserFirstName UserLastName].
      
      SAME error occurs when using TFSSecurity.exe and "TFS Administration Tool 2.1"
      
      The work around is to run the g- command and then the g+ command even though TFSSecurity does not list the user!
      
      Has anyone experienced this issue?
      
      Much appreciatedl.
      
      
  • Don't for 'Build Failure' as a reason on bud before RTM
    6 Posts | Last post May 09, 2011
    • The current version of the template does not work with Team build. Team build cannot create a bug because the reason 'Build Failure' is missing see error below.  Granted it is a easy customization (which I have already made) however, it should be in all templates so Team build does not error out.
      
      TF42097: A work item could not be created due to a field error. The following fields have incorrect values: Field: 'Reason' Value: 'Build Failure'
      
      Donovan
    • Sorry for typos I was in a hurry.  Title should be "Don't forget 'Build Failure' as a reason on bug before RTM"
    • Thanks Dononvan.  We're fixing...
    • Glad to hear.  It appears you instead of using the out of the box priority field you created a new one for Backlog priority which leads to the following.
      
      TF42095: Failed to update 'Priority' field. Error message: TF26027: A field definition Priority in the work item type definition file does not exist. Add a definition for this field or remove the reference to the field and try again.
      
      You may consider using the built in priority field common to the majority of templates and just changing the label to Backlog Priority on the screen.  I simply updated my build template to not set the priority and allowing Backlog Priority to take the default value. 
      
    • One more thing about bugs created during the build. Once you add the “'Build Failure” reason and remove the Priority assignment from the build template none of the bugs are owned by anyone.  The build template is trying to set AssignedTo. 
    • Did you released a fix for those issues ? I still experience them ???
  • No Team Sprint
    1 Posts | Last post April 30, 2011
    • One thing that you have missed in this wonderfull template is the team sprint in case of more than one team in a sprint
21 - 30 of 121 Items