Microsoft Visual Studio Scrum 1.0

Microsoft Free

A new Team Foundation Server process template for Scrum teams. Product Backlog Items, Sprints, Velocity, Sprint Burndown...

Microsoft
(46) Review
Visual Studio
2010
Download (137,730)
11/4/2010
1.0
E-mail Twitter del.icio.us Digg Facebook
Add to favorites
Description
Reviews (46)
Q and A (121)
Sign in to write a review
Sort by:

by David Musselman | October 02 2013

Is there a version of this for Scrum 2.2?

by D. Chatterjee | May 20 2013

Seems good, does this supports all charts?

by Sergio Parra | April 27 2013

Really a very good template!

by M.Radwan-MVP | August 23 2012

by FizzCyp | July 19 2012

by Laurent Jordi Innovacall | June 30 2012

Hello,
I know this process template is well done and necessary for my team BUT !
It doesn't work on a french TFS Server with it's french portal.
I tryed 1000 things I still have the TF249033 error

le modèle de site n'est pas disponible pour l'identificateur de paramètres régionaux (LCID). Le nom du modèle de site est : TFS2010 Agile Dashboard. Le LCID est : 1033. (type TeamFoundationServerException)

The process template is not available for this LCID... bla bla bla ... LCID is 1033

I absolutely need this process template and the sharepoint and reporting services.

Please, publish a procedure to install this project template on a French TFS Server.

Best regards,

Laurent

by usjunior | June 22 2012

by Mr. Wharty | June 08 2012

Thanks for posting

by DRiley5998 | June 01 2012

Will not install,

Event Description: TF30162: Task "WITs" from Group "WorkItemTracking" failed
Exception Type: Microsoft.TeamFoundation.Client.PcwException
Exception Message: Object reference not set to an instance of an object

by ezien | May 08 2012

by Dragan Radovac | May 06 2012

by Mattias Sköld | May 05 2012

A good template for running scrum projects, the burndown detects current sprint and makes it much easier to change sprint.
One thing that could be improved is support for multiple teams.

by Sofwarer | April 30 2012

iyi bir eklenti olmuş

by Ahmed Naji | April 02 2012

This is great template,our productivity increased now
Thank you Microsoft

by Code Chief | February 05 2012

Use this template as standard for all projects. SCRUM is great!

by TerrenceCheng | January 14 2012

Great job!.
But i have a question. today is the end of a scrum project. I want an amount of all initial task time. so that i can get if my team member's work good or bad. and so that i can make a report to my boss: how much works we finished.

now, in this project, the "remaining work" field is changed from "10" to "3", at last, when the state changed to "Done", the remaining work field's value is no longer exist.

how could i get the initial "remain work" value ?

thanks in advance.

by dsnook2 | November 10 2011

by Daniel Cheida | November 06 2011

Favorite

by Bob Cornelissen | September 04 2011

Thanks for adding this

by mfrederiksen | August 19 2011

Cool simple Scrum template.

1 - 20 of 46 Items   
Sign in to start a discussion


  • Scrum template does not appear in the process template list after installation
    2 Posts | Last post February 14, 2011
    • Hi,
      
      I have downloaded and installed the Scrum template according to the installation instructions. (No error messages receive during installation)
      
      Next step is to create a new project that uses Scrum template instead of Agile template. My problem is that the Scrum template does not appear in the list of possible templates.
      
      I have been using TFS as end user for a while, but I have never administrated a TFS server. I don't know how to solve this issue....
      
      BR,
      Allis
    • After all, I have not read the installation guide properly. I can select the template:-)
  • Excluding Weekends from Sprint Burndown
    8 Posts | Last post January 31, 2011
    • Are you planning to add an option to the Sprint Burndown report to exclude weekends?
    • 2re
      Hi Leo
      
      I needed that as well and found a workaround. I have changed the trendline to be flat in weekends. It is not that tricky to do since the code behind it is visual basic and the rdl file can be edited in a normal text editor.
      
      Here is a way to do this.
      
      1. Right click Reports in your team project and select "Show report site".
      2. Find the Sprint Burndown file and click the triangle in the right side of it.
      3. Select "Download" and place it somewhere on your local disk.
      4. Open the downloaded file in your favorite text/xml editor
      5. Search for "Function Burndown" and replace the entire function with two functions in my next post.
      6. Save the file and upload it by selecting "Upload file" on the Report Site
      7. Sometimes the Data Sources gets changed when downloading. You can fix this on the Report Site by clicking "Manage" from the triangle menu on your file. Look for the Data Sources tab and browse to the correct data sources.
      
      Enjoy!
      
      / Tore Østergaard
    • 2re
          Function Burndown(ByVal val As Object, ByVal valDate As Date, ByVal endDate As Date)
              If valDate 
    • 2re
          Function Burndown(ByVal val As Object, ByVal valDate As Date, ByVal endDate As Date)
              If valDate < firstDate Then
                  firstValue = Double.NaN
                  firstDate = DateTime.MinValue
              End If
      
              If Double.IsNaN(firstValue) Then
                  If Not val Is Nothing And val <> 0 Then
                      firstValue = val
                      firstDate = valDate
                      numDays = Math.Max(1, Weekdays(valDate, endDate))
      
                      Return firstValue
                  End If
              Else
                  Return (Weekdays(valDate, endDate) / numDays) * firstValue
              End If
      
              Return Nothing
          End Function
      
          Function Weekdays(ByVal fromDate As Date, ByVal toDate As Date)
              Dim i As Integer
              Dim intTotalDays As Integer
              Dim intWeekDayCount As Integer = 0
              intTotalDays = DateDiff(DateInterval.Day, fromDate, toDate)
      
              For i = 1 To intTotalDays
                  If Weekday(DateAdd(DateInterval.Day, i, fromDate), FirstDayOfWeek.Monday) < 6 Then
                      intWeekDayCount = intWeekDayCount   1
                  End If
              Next i
      
              Return intWeekDayCount
          End Function
    • 2re
      Sorry for the extra posts... You need to web incode the < and > signs in order for it to work. I had to make back into the "real" characters in order to be able to post them here.
    • Awesome! I tried it and I got the following error: There is an error on line 35 of custom code: [BC30205] End of statement expected. (rsCompilerErrorInCode) 
       
      Could it be that the line "Weekday(DateAdd(DateInterval.Day, i, fromDate), FirstDayOfWeek.Monday) < 6" is meant to call "Weekdays" instead of "Weekday"? Thanks!
    • I found the error. The problem is in the next line "intWeekDayCount = intWeekDayCount 1". It is missing the " " as in "intWeekDayCount = intWeekDayCount   1". It loaded now.
      
      When I run the report it shows a flat line for each weekend day. Is there a way to exclude these weekend days altogether? This is good. It's almost there. Thanks for sharing!
    • OK. That last post removed characters also. I was trying to put the plus (
  • How can I hide or delete out the Sprint work item type?
    1 Posts | Last post January 31, 2011
    • My boss does not want it to appear to the team as a work item option. I don' mind hiding it from everyone's view, or deleting it. However, deleting it from the Process Template Editor causes the Project Creation to fail, as it is looking for Sprint.xml
  • How to use properly product backlog items and tasks to reflect it to the sprint burndown report
    6 Posts | Last post January 23, 2011
    • What is the proper way to use product backlog items and tasks, to get correct results (or results at all) to the sprint burndown report?
      
      For example I have created a product backlog work item X and have added some tasks to it. Then I have set the Iteration value of the product backlog item to sprint we are on currently and assigned the item to someone + state of the item is 'Committed'.
      
      So now I have sprint backlog item with some tasks in the TODO state. If I now run the sprint burndown report, I have nothing (I used the web services according to MSDN instruction to get the data available for reports).
      
      So what I try to ask is, what do I need to change and set, so that I will get correct results to the sprint burndown report?
      
      Does the tasks need to be assigned to someone? Does the remaining work of a task need to be set also? If a tasks remaining work is always hours, how does it reflect to the backlog item effort or is there any relation with this?
      
      Should backlog item be assigned to the product owner always and tasks to developers or to anyone who is going to complete the task?
      
      Just trying to understand how we are supposed to use the template to get the best out of it and not just have it as something people need to do and get no benefit out of it ;)
    • 2re
      Hi Kornelius
      
      I will try to answer some of your questions.
      
      The Sprint Burndown report will show you a summarization of the Remaining Work of all tasks that have the Iteration Path set to the selected sprint.
      
      There are no relations enforced by the template between Effort on a Product Backlog Item and Remaining Work on a Task. This is really something that your team decides upon. Usually Effort (by some called Story Points) is a product owner term which uses any unit. Remaining Work is used by developers to track what is left in the current sprint and is usually in the unit of man hours. The product owner can then observe the velocity of Effort done in each sprint and then estimate how many tasks can be done for each release.
      
      Hope that this helps a bit.
      
      / Tore Østergaard
    • Hi
      
      Thanks for the reply. This confirmed what I thought (after I had experiment enough with the to do and inprogress states of a task and setting the remaining work for all of them).
    • My problem with this chart is that the assignment of work items to the iteration (sprint backlog) must be done at precisely on or before the first day of a sprint, otherwise the chart looks like a two-sloped mountain, not a right-triangle one is expecting.
      Sometimes it happens that we update TFS a day or two later (the tasks are already on the white board and being worked on) and as far as I can see there is no way to assign the sprint items retroactively - TFS always timestamps them with the current date.  
      
      Would be nice to be able to specify the beginning date of a task.
    • 2re
      Hi aoleynikov
      
      With the danger of sounding religious (or ridiculous :-) I will answer that updating the tasks retrospectively is not really how Scrum is done. You are supposed only to look ahead and see what work is remaining.
      
      You are right though, that it could be a problem that the burndown is calculated static based on the data on the sprint start date, if one forgets to assign tasks to the iteration. We solve this by using a query to plan your work that only shows tasks that are included in the sprint you are planning for.
      
      /Tore Østergaard
    • @Kornelius -
      
      Sounds like you are on the right path, did you create an actual Sprint Workitem with the start and end date of your sprint?  You have to create one for every sprint and is key to the burndown chart.
      
      Hope this helps!
      
      Christe
  • TFS 2010 & Visual Studio 2008
    1 Posts | Last post January 18, 2011
    • We really want to use this template and are moving to TFS 2010 for it. We cannot however afford to move to Visual Studio 2010 yet. Is TFS the only requirement? Will this work with TFS 2010 and Visual Studio 2008?
  • Impossible to create a team project with the Microsoft Scrum process template
    1 Posts | Last post January 11, 2011
    • Hello,
      
      I deployed TFS2010 x64 french with SharePoint Services 3.0 French by default on a single server with Windows Server 2008 R2 x64 French, SQL Server 2008 R2 Standard x64 French.
      Then I installed the Microsoft Scrum Process Template 1.0.
      
      But when I try to create a Team project with the Scrum process template from a Visual Studio 2010 French on a client machine, I get the TF249033 error on SharePoint :
      
      "le modèle de site n'est pas disponible pour l'identificateur de paramètres régionaux (LCID). Le nom du modéle de site est : TFS2010 Agile Dashboard. Le LCID est : 1033. (type TeamFoundationServerException)
      
      English translation : The site template is not available for the locale identifier (LCID). The site template name is: TFS2010 Agile Dashboard. The LCID is: 1033. (Typ TeamFoundationServerException)
      
      I installed the English language pack for SharePoint Services 3.0 + English Langage pack SP2, but the problem is always the same.
      
      Thank you for your help.
  • Next version
    2 Posts | Last post January 09, 2011
    • When will the next version be available? I would like to find a way to easily keep track/record daily standup questions/answers.
      
      
    • Any news on the next version with workbooks?
  • C:\Temp\Microsoft_Visual_Studio_Scrum_1.0[1].msi
    1 Posts | Last post December 30, 2010
    • Hi,
      I just downloaded and tried to install this.  There's a bug in the install where it's insisting on looking for the install program at C:\Temp\Microsoft_Visual_Studio_Scrum_1.0[1].msi.  I tried renaming the install and putting it in THAT location, and it installed.
      
      Just an FYI...
      
      Now to figure out where the heck is it...  :)
      
  • Merry Christmas
    2 Posts | Last post December 29, 2010
    • 2re
      I wounder if I will find a Microsoft Visual Studio Scrum 1.5 under the christmas tree anytime soon?!
    • Hopefully soon, with excel workbooks too!
  • Versioning of this Template
    1 Posts | Last post December 14, 2010
    • Why are there updates to this template without a version change?
      
      If you are going to change it (ie add a project portal, etc) you need to up the version and include a change list.
      
      I get bored of doing a diff on each part of the template each time the "Last Updated" changes.  (Especially because I had to customize the template.)
41 - 50 of 121 Items